There is much progress to report. Forms have been stripped from the foundation walls in the connector. Backfilling will begin this week. Steel is scheduled to go up on Monday, July 1. Structural fill and lower slab pour will follow. The second floor above the Stokey/Sears room now exists. Windows on the south wall of the Stokey/Sears room have been lowered.

View of the former high-ceiling space in Stokey library showing the new floor of the new classroom above