There is much progress to report. Forms have been stripped from the foundation walls in the connector. Backfilling will begin this week. Steel is scheduled to go up on Monday, July 1. Structural fill and lower slab pour will follow. The second floor above the Stokey/Sears room now exists. Windows on the south wall of the Stokey/Sears room have been lowered.

Foundation walls looking towards the parish house

Connector foundation walls looking towards meetinghouse

Rear entrance to parish house

Installing new sills on relocated windows in Stokey library

Inside Stokey library showing the windows in their new locations

Inside Stokey library

View of the former high-ceiling space in Stokey library showing the new floor of the new classroom above

View from stairwell of new emergency exit door from new classroom into stairwell

Brand new classroom on the second floor

Interior of new classroom formed by eliminating high-ceiling space in Stokey library